Project 1c: JP8 Permanent Purge Fluid Station Randolph AFB, Texas

Project 1c: JP8 Permanent Purge Fluid Station

Randolph AFB, Texas 

E-Corp completed this seven-month USAF Hill AFB design-build project in October 2012. This JP8/purge fluid distillation system included installation of the following:

  • 12,000-gallon purge fluid tank
  • 12,000-gallon contaminated fluid tank
  • Both tanks are double wall UL-142 “Flameshield” and have self-contained control panel, meter, shut-off values, circulation pumps, piping, retractable aircraft hoses and connections.
  • 2,500-SF concrete pad
  • Electrical service and panels

This system is capable of 24-hour operation servicing any fighter and transport aircraft in the DoD with a fuel tank capacity up to 10,000 gallons.                      

       

Project Cost:

$546,000.00            

Aircraft Recovering Time:

As little as 2 hours

Environmental Impact:

0